Assume that you are given the job of project manager for building a new
student center on your campus.
List just five of the major activities
that need to be accomplished to complete the new building in two years.
Draw an AON network diagram that links the activities together in
required event scheduling and sequencing.
Make an estimate for the time
required for each sequence to be completed and identify the critical
path.
There are a very large number of activities required to complete a new student center building on a college campus. Among them, one might expect the following to be core requirements:
ReplyDelete(1) land surveys and planning permissions from local government,
(2) architect plans developed and approved,
(3) major subcontractors hired,
(4) site excavation completed,
(5) building exterior com pleted,
(6) building interior completed and furnishings installed.
Use the figure from the chapter as a guide for developing your AON diagram.